Two legal routes to the same content
Directive 1999/92/EC, known as ATEX 153 (formerly ATEX 137), covers workplaces where explosive atmospheres may occur. Article 8 asks the employer to draw up an explosion protection document before work begins, keep it up to date, and revise it after significant changes, extensions or conversions; existing assessments may be combined into it. Member states put this into their own law. In Germany the Explosionsschutzdokument is part of the risk assessment under § 6(9) of the Gefahrstoffverordnung (GefStoffV). In the Netherlands the explosieveiligheidsdocument (EVD) is written under article 3.5c of the Arbobesluit as part of the employer's risk inventory and evaluation (RI&E), with no prescribed format. In Ireland it is the explosion protection document of Regulation 169 of the General Application Regulations 2007.
In Great Britain the Dangerous Substances and Explosive Atmospheres Regulations 2002 (DSEAR) require a suitable and sufficient risk assessment (regulation 5), a record of its significant findings where five or more people are employed, and the classification of hazardous places into zones (regulation 7). L138 notes that the directive's document is not a separate requirement in Great Britain, because regulations 5, 6 and 7 already cover the information. Northern Ireland has the same provisions in DSEAR (Northern Ireland) 2003. Equipment is a separate regime: Directive 2014/34/EU (ATEX 114) in the EU, the Equipment and Protective Systems Regulations 2016 in Great Britain.
The assessment behind the document
Both forms rest on the same assessment: how likely an explosive atmosphere is and how long it persists; how likely ignition sources, including electrostatic discharges, are to be present and become effective; the installations, substances, processes and their interactions; and the scale of the foreseeable effects. Places connected through openings to a hazardous place are included (DSEAR regulation 5(2); Arbobesluit article 3.5c(3)), and DSEAR adds the hazardous properties of the substance, its safety data sheet, the amount present and high-risk activities such as maintenance.
No licence is required for the person who carries out the assessment; the texts ask for competence. L138 says that whoever carries it out should be competent, and the Management of Health and Safety at Work Regulations prefer a competent person from the employer's own staff where one is available. Germany goes further: § 6(11) GefStoffV allows only fachkundige persons, and under § 19(4) the authority can ask for proof. Detail should match the risk; L138 allows measures to be recorded by reference to other documents.
Zones and the zone drawing
Hazardous places are classified into zones by how often and how long an explosive atmosphere is present: Zones 0, 1 and 2 for gases, vapours and mists; Zones 20, 21 and 22 for combustible dusts (Annex I of the directive; DSEAR Schedule 2). Normal operation means use within the design parameters, and layers, deposits and heaps of combustible dust count as sources.
The regulations do not prescribe a calculation method. Zones are normally calculated to IEC 60079-10-1 for gases and vapours and IEC 60079-10-2 for dusts (BS EN IEC 60079-10-1:2021 and BS EN 60079-10-2:2015 in the UK); the Energy Institute's Model Code of Safe Practice Part 15 covers installations handling flammable fluids, and the Netherlands Labour Authority assesses against the NEN-EN-IEC 60079 series and NPR 7910-1 and -2. Whatever the method, each zone should rest on a source of release, a release rate, the ventilation and written assumptions.
L138 lists the zone classification among the contents of the DSEAR record, and the verification it describes includes checking that a hazardous area classification drawing has been prepared. In Germany the zones must be documented in the explosion protection document (Annex I No. 1.7 GefStoffV); KomNet, the advisory service of the North Rhine-Westphalia labour protection authorities, answers that the ordinance does not demand a graphical zone plan, while DGUV Information 213-106 lists the plans that normally accompany the document. A drawing is the quickest way for an inspector, a contractor or a new operator to see the zones, so every document we prepare has one.
Equipment and ignition sources
Equipment categories follow the zones: category 1 in Zone 0 or 20; category 1 or 2 in Zone 1 or 21; category 1, 2 or 3 in Zone 2 or 22 (Annex II of the directive; DSEAR Schedule 3). In Ireland, Regulation 172 allows equipment into use only where the explosion protection document indicates that it can be used safely.
A complete document does not stop at the Ex marking. It compares equipment group and temperature class with the substances present, and it assesses ignition sources beyond electrical equipment, such as hot surfaces, mechanical sparks, static electricity and non-electrical equipment (EN ISO 80079-36), using the ignition source types of EN 1127-1.
Measures, coordination and records
The measures follow the order of priority in Article 3 of the directive: prevent the explosive atmosphere, avoid its ignition, limit the effects of an explosion. The document states which measure applies where and who is responsible for it. Organisational measures belong in it too: training, written instructions and permits to work where the document calls for them, work clothing that does not cause electrostatic discharges, and the black-on-yellow warning triangle at the entrances to hazardous places (DSEAR Schedule 4; Annex III of the directive).
Where several employers share a workplace, for example contractors during a shutdown, the document records the aim of the coordination and how it is carried out (DSEAR regulations 5(4) and 11; Article 6 of the directive). In Germany the technical measures are checked regularly and at least every third year (§ 7(7) GefStoffV).
Verification before first use
Before a workplace with hazardous places is first used, its overall explosion safety has to be verified by a person competent in explosion protection. In Great Britain this is DSEAR regulation 7(4), and the record shows that it was done. L138 describes the method: examination of documents, visual inspection, and physical checks and measurements, usually as part of commissioning; the employer's own staff may do it if they are impartial, and L138 recommends recording the verifier's name and the date. The equivalents are Regulation 170(2) in Ireland and article 3.5e of the Arbobesluit in the Netherlands.
In Germany installations in hazardous areas are inspected before commissioning and at least every six years, taking the explosion protection document and the zones into account: by an approved inspection body (ZÜS) for installations that need a permit, such as filling stations and large stores of flammable liquids, otherwise also by a zur Prüfung befähigte Person (§ 15(3) and Annex 2 Section 3 of the Betriebssicherheitsverordnung).
This step happens on site. A document prepared from drawings should list what the verifier has to check, so the verification is complete and quick to record.
Keeping it current
Neither DSEAR nor the German ordinance sets a fixed interval: DSEAR regulation 5(3) asks for regular review and review after significant changes, and § 6(10) GefStoffV for regular review and an update without delay after changes. Ireland's Health and Safety Authority recommends an annual review of the risk assessment as good practice. Fixed cycles quoted in the market, such as every three or five years, are policy or advice, not law. What matters is the trigger: a new substance, process step or building, or a change to ventilation, calls for a revision, best completed before the changed plant starts up.
Side by side
| Element | Great Britain: DSEAR | EU: explosion protection document |
|---|---|---|
| Legal basis | DSEAR 2002, regulations 5 and 7; L138 | Directive 1999/92/EC, Article 8, in national law: for example § 6(9) GefStoffV, Arbobesluit article 3.5c, S.I. 299/2007 Regulation 169 |
| What is written | Record of significant findings where five or more are employed | A written document, which may combine existing assessments; in the Netherlands part of the RI&E |
| Who prepares it | The employer, with competent help; no licence | The employer; Germany requires fachkundige persons and proof on request |
| Zones | Regulation 7, Schedule 2; drawing part of the record | Article 7, Annex I; zones documented in the document |
| Equipment | Categories by zone, Schedule 3 | Categories by zone, Annex II |
| Before first use | Verification under regulation 7(4) | Verification under the national rule; in Germany inspection by a ZÜS or a befähigte Person |
| Review | Regularly and after significant change | After significant change; Germany adds regular review |
| Language | No rule; English in practice | Germany: German in practice; Netherlands: no rule, Dutch in practice |
Gaps worth checking in an existing document
- Zones drawn from a template or a rule of thumb, with no source of release, release rate or ventilation behind them.
- Substance data that do not match the safety data sheets in use.
- Dust layers and deposits, and rooms connected through openings, left out.
- Ignition sources limited to electrical equipment.
- An equipment list that checks the Ex marking but not group and temperature class against the substance.
- No record of coordination with contractors, or of the verification before first use.
- A generic assessment copied from another site and never adapted to this one.
- No revision after a change to substances, process, building or ventilation.
How we prepare and review these documents
We prepare both forms from your documents: process descriptions, safety data sheets, layouts and P&IDs, ventilation data and the equipment list, with photographs and measurements collected by your team using our checklist. The structure follows the rules that apply to the plant. Every zone has its calculation and every assumption is written down, so the person who verifies the site can check it.
We do not visit sites outside Türkiye, and our work does not replace the verification before first use or the inspections your country requires; the report lists what they should check and states what was verified on site and what was not. The document remains the employer's: your competent person or consultant reviews and adopts it. See explosion risk assessment, hazardous area classification, the independent review of an existing document, and support for consultancies.
Frequently asked questions
Does a site in Great Britain need an explosion protection document?
Not under that name. DSEAR requires a risk assessment, a record of its significant findings and a zone classification, and L138 states that these cover the same information. A group with plants in the EU and Great Britain can keep one structure and map each section to the national requirement.
Is a DSEAR risk assessment the same as hazardous area classification?
No. Hazardous area classification is an integral part of the DSEAR risk assessment, but the assessment also covers substances, ignition sources, measures, coordination, verification and review.
Who can prepare these documents?
The employer is responsible and adopts the document. In Great Britain, Ireland and the Netherlands no licence is required for the preparer; the measure is competence. Germany requires a fachkundige Person, and the authority can ask for proof. An external engineer may prepare it, but someone on the employer's side has to own it.
Can the document be prepared without a site visit?
The assessment, calculations and drawings can be prepared from documents, data and photographs; none of the texts discussed here requires the preparer to be on site. The verification before first use and the inspections each country requires are done on site, so a remotely prepared document should state what was verified on site and what was not.
In which language should it be written?
In Great Britain and Ireland, English. In Germany no clause fixes the language, but the authorities work in German and instructions must be understandable to workers, so a German version is expected in practice; in the Netherlands, Dutch is usual. Where German is needed, draft sections, the executive summary and the measures can be provided in German, marked as a technical translation.
Sources
- Directive 1999/92/EC (ATEX 153), Articles 3, 4, 6, 7 and 8; Annexes I, II and III
- Dangerous Substances and Explosive Atmospheres Regulations 2002 (SI 2002/2776), regulations 5, 7 and 11; Schedules 2 to 4. DSEAR (Northern Ireland) 2003 (SR 2003/152)
- HSE, L138 Dangerous substances and explosive atmospheres: Approved Code of Practice and guidance, second edition 2013; HSE, Explosive atmospheres: classification of hazardous areas (zoning) and selection of equipment
- Management of Health and Safety at Work Regulations 1999, regulation 7
- Gefahrstoffverordnung (GefStoffV) §§ 6, 7, 12, 19 and Annex I No. 1.7; Betriebssicherheitsverordnung (BetrSichV) §§ 15, 18 and Annex 2 Section 3; DGUV Information 213-106 Explosionsschutzdokument (06/2021); KomNet (North Rhine-Westphalia)
- Arbeidsomstandighedenbesluit (Arbobesluit) articles 3.5a to 3.5f; Arbeidsomstandighedenwet article 5; Netherlands Labour Authority work instructions on gas and dust explosion hazards
- Safety, Health and Welfare at Work (General Application) Regulations 2007 (S.I. No. 299 of 2007), Part 8, Regulations 169 to 175 and Schedule 10; HSA, Guide to Part 8 of the General Application Regulations 2007
- IEC 60079-10-1 and IEC 60079-10-2 (BS EN IEC 60079-10-1:2021, BS EN 60079-10-2:2015); NPR 7910-1 and NPR 7910-2; Energy Institute Model Code of Safe Practice Part 15; EN 1127-1; EN ISO 80079-36
Cite this article: Anac, O. F. (2026). DSEAR risk assessment and explosion protection document: what each must contain. Axosfer, https://axosfer.com/en/guide/dsear-risk-assessment-explosion-protection-document/ (last updated 13 November 2026).